Removal of asbestos – containing parts from the ship
REMOVED MATERIALS: gaskets and spare parts
The data used is taken from the project plan and from the IHM report (reference: 19.120018, version 1.0)
FINDINGS OF THE VISUAL INSPECTION:
The removal of the asbestos is performed correctly, in accordance with current Latvian standards, laws and regulations.
LIMITATIONS AND / OR EXCLUSIONS FROM THE VISUAL INSPECTION:
The entire Vessel, except for the designated installation components where the removal is carried out.
CONCLUSIE VAN DE VISUELE INSPECTIE:
The working area meets the requirements as set in NEN 2990. The work area is visually approved.
The gaskets and spare parts have been completely removed and double packed.
- YEAR 2021
- WE DID Dismantling and disposal
- CATEGORY Asbestos containing elements utilization , Asbestos waste transport , Pollution localization , Removal of asbestos from the ship , Space purification , Space sealing
- TAGS Asbestos , Dismantling , Ship
Related Projects
RAIL BALTICA
During the construction works of Rail Baltica Riga Central Station,…
Latvian Television (LTV)
Dismantling works: Sampling; Cleaning of the object from asbestos-containing materials.
British Embassy Riga
Estimate: Laboratory sampling; Laboratory services – Determination of asbestos fibers…