LONGVIND, IMO 9547336
Wednesday, 17 February 2021
by Miks Lejins
REMOVED MATERIALS: gaskets and spare parts
The data used is taken from the project plan and from the IHM report (reference: 19.120018, version 1.0)
FINDINGS OF THE VISUAL INSPECTION:
The removal of the asbestos is performed correctly, in accordance with current Latvian standards, laws and regulations.
LIMITATIONS AND / OR EXCLUSIONS FROM THE VISUAL INSPECTION:
The entire Vessel, except for the designated installation components where the removal is carried out.
CONCLUSIE VAN DE VISUELE INSPECTIE:
The working area meets the requirements as set in NEN 2990. The work area is visually approved.
The gaskets and spare parts have been completely removed and double packed.
Rail Baltica
Wednesday, 17 February 2021
by Miks Lejins
During the construction works of Rail Baltica Riga Central Station, the builders have discovered asbestos remnants during the transfer of engineering communications networks. Hazardous material has been collected and taken to a landfill for hazardous waste, subject to all safety precautions. These works required an additional working week.
In the first stage of Rail Baltica Riga Central Unit works, engineering communications will be transferred, a new transformer station will be built, as well as preparations for platforms - reconstruction of signaling, cable and switches, as well as demolition of some underground structures.
AS Putnu fabrika, Kekava
Friday, 15 January 2021
by Miks Lejins
Object “Demolition of the boiler house building”, at the address “AS Putnu fabrika Ķekava ”, Ķekava, Ķekava parish, Ķekava district, land cadastre number 8070 008 1288 work organization project developed on the basis of the developed construction plan data, construction norms and Latvian state standards
Latvian Television (LTV)
Wednesday, 19 August 2020
by Miks Lejins
Dismantling works: Sampling; Cleaning of the object from asbestos-containing materials.
Heat plant “Daugavgriva”
Friday, 02 August 2019
by Miks Lejins
Contract – Proper dismantling and wrapping of existing pipes in airtight containers, taking all health and environmental precautions into account; Removal of heat insulation from boilers and chimneys, wrapping in sealed packages, removal, collection in containers; Sealing and sealing of surrounding space and environment; Asbestos collection and recovery at the Broceni landfill; 1 floor construct
Museum of the Occupation of Latvia
Friday, 02 August 2019
by Miks Lejins
Contract – asbestos-containing construction products and the dismantling and recycling, hereinafter – Works, the apartment and put the construction works to the Customer under this Agreement, technical specifications, construction projects and existing regulations.
State Joint Stock Company “Latvijas dzelzcels”
Friday, 02 August 2019
by Miks Lejins
Contract – collection of hazardous waste.
Skanstes street 52 un 52a, Riga
Friday, 02 August 2019
by Miks Lejins
Contract – dismantling of asbestos cement cable sewer pipes according to EST-03; the accumulation of asbestos cement pipes resulting from dismantling operations and their disposal at a landfill containing asbestos-containing waste; the accumulation and removal of waste resulting from dismantling operations.
Skanstes street 52, Skanstes street 52A and Skanstes street 50A, Riga
Friday, 02 August 2019
by Miks Lejins
Contract – dismantling of thermal insulation of heating pipelines; removal of asbestos cladding of contaminated materials – utilizable pipelines; the asbestos waste resulting from the dismantling operations of the storage and disposal of asbestos-containing landfill; sealing and sealing of surrounding spaces. Development of additional cameras; removal and removal of thermal insulation, collection in containers; utilization
Riga Technical University
Thursday, 01 August 2019
by Miks Lejins
Contract – dismantling of metal structural elements in basement premises; dismantling of insulation materials; dismantling of metal pipes; dismantling of asbestos insulation; the asbestos waste resulting from the dismantling operations of the storage and disposal of asbestos-containing landfill; the accumulation and removal of waste resulting from dismantling operations. Riga Technical University, Engineering and Intelligent Technology